SB 2008-02
Rhode Island Reliability Project - National Grid
- Transmittal Letter
- Application (Because of the size of the files involved, the figures referenced in the application are not directly available on-line. To request an electronic version of any figure click here.)
- Docketing Notice
- Notice of Preliminary Hearing (Scheduled for November 12, 2008)
- Preliminary Decision and Order (12/19/08)
- PUC Transfers Docket 4029 to EFSB
- EFSB Issues Notice of Public and Final Hearings
- EFSB Issues Order 63 (re: Discovery Motions)
- EFSB Issues Notice of Final Hearings (which commence Monday, October 19 at 9:30 AM)
- Notice of Final Hearing
- Notice of Final Hearing (continued on May 20, 2010)
EFSB Issues Final Decision and Order (August 12, 2010)
(Additional filings from parties in this Docket may be listed at the Commission Docket 4029 page)
National Grid Filings
- Prefiled Testimony March 13, 2009- Attachment A - Attachment B
- Rebuttal Testimony Transmittal Letter and Index
- Filing in Accordance with RIGL §42-98--9.1(b) and EFSB Rule 1.8(h)
- Hearing Presentations
- Prefiled Testimony (June 29, 2009) Transmittal Letter - Index
Exhibits Introduced at July 14, 2009 Hearing
National Grid 21- Route Statistics
- National Grid 22 - State of Connecticut Siting Council Supplemental Testimony III of Dr. William H. Bailey - Concerning Magnetic Field Exposure Policy
- National Grid 23 - State of Connecticut Siting Council Supplemental Testimony V of Drs. William H. Bailey and Philip Cole
- National Grid 24-48 Hour Magnetic Field Exposure
- National Grid 25 - Magnetic Field at Average Annual Loading
- National Grid 26 - Significant Underground Transmission Outage
Exhibits Introduced at May 20, 2010 Hearing
- Supplemental Testimony of David J. Beron, P.E., P.M.P. and attachments (9/28/09)
- Testimony of Joseph M. Drouin, P.E. and attachment
- Supplemental Testimony of David J. Beron, P.E., P.M.P. and attachments (4/27/10)
- National Grid 35 - Project Schedule
- National Grid 36 - Cross-Section Cranston/West Warwick Boundary
- National Grid 37 - West Warwick Alternative Pole Schematic
- National Grid 38 - West Warwick Alternative Easement Schematic
ISO-New England Filings
Responses to Data Requests - Record Requests
- National Grid - Response to Johnston's First Set of Data Requests
- National Grid - Response to Johnston's Second Set of Data Requests
- National Grid - Response to EFSB's First Set of Data Requests
- National Grid - Response to Johnston's Third Set of Data Requests
- National Grid - Response to EFSB's Record Requests (July 24,2009)
- National Grid - Response to EFSB's Second Set of Data Requests
Planning and Zoning Filings
- City of Cranston Zoning Board
- Town of West Warwick Building/Zoning Official
- Town of West Warwick Planning Board
- Town of West Warwick Zoning Board
- City of Warwick Advisory Opinion
- Statewide Planning Program Advisory Opinion
- Town of Smithfield Zoning Board
- Town of Johnston Advisory Opinion
Additional Prefiled Testimony
Advisory Opinions
- Evaluation of Evidence Presented by National Grid Related to Potential Health Effects of Rhode Island Reliability Project - Kenneth R. Foster and Associates
Post Final Hearing Briefs, Memoranda and Settlement Stipulation