Docket No. 4981 - Episcopal Diocese of Rhode Island (EDRI) - Petition for Declaratory Judgment on Transmission System Costs and Related "Affected System Operator" Studies (filed 10/11/19)
Status of Docket: Closed.
Filings relating to proceeding in response to Supreme Court Remand Order (March 2021):
- Supreme Court Remand Order
- Commission request for information and procedural schedule (4/15/21)
- EDRI objection to procedural schedule (4/21/21)
- PUC response to EDRI objection (4/27/21)
- EDRI letter regarding procedural questions (4/27/21)
- Commission Clerk response to EDRI (4/28/21)
- Commission Clerk response to EDRI (4/28/21)
- Division of Public Utilities' (Division) Response to Episcopal Diocese RI (4/23/21)
- EDRI's Brief on Remand (5/6/21)
- Narragansett Electric d/b/a National Grid's Response Brief (5/14/21)
- Division's Response Brief (5/14/21)
- EDRI Reply Brief on Remand (5/26/21)
- PUC - Atty. Lucarelli Memo to Parties (5/19/21)
- PUC Notice of Oral Arguments - on June 2, 2021
- EDRI's Motion for Recusal, Withdrawal of Notice and Further Assurance Against Bias (5/24/21)
- National Grid's response to the May 19, 2021 Notice of Inclusion of Certain Documents from Docket 4973 Into
the Record and Request to Update Information Stated in Petitioner’s Brief (5/24/21) - PUC Order No. 24061 denying EDRI's Motion for Recusal (6/3/21)
- EDRI's Data Request to Division (4/14/21)
- Division's Objection to all of EDRI's Data Requests (4/23/21)
- EDRI's Prefiled Testimony of David Burton (5/25/21)
- EDRI's Pefiled Testimony of Kenneth Payne (5/25/21)
- EDRI's Pefiled Testimony of John Farrell and Karl Rabago (5/25/21)
- EDRI's Pefiled Testimony of Fred Unger (5/25/21)
- EDRI's Pefiled Testimony of Matt Ursillo (5/25/21)
- EDRI's Pefiled Testimony of Scott Milnes (5/25/21)
- Division's Objection and Motion to Quash (6/1/21)
- National Grid's Motion to Strike (6/2/21)
- EDRI's Motion for Reconsideration (6/7/21)
- National Grid's Objection to EDRI's Motion for Reconsideration (6/9/21)
- PUC Order No. 24089 issued in response to the Supreme Court Remand Order dated March 24, 2021. Remand Order issued 7/14/21.
Filings relating to proceeding prior to Supreme Court Appeal (May 2020):
- Episcopal Diocese's Petition
- Agreed Facts between the Episcopal Diocese and The Narragansett Electric Co. d/b/a National Grid
- Procedural Schedule
- PUC Notice to Solicit Comments and Intervention Deadline
- PUC Second Notice to Solicit Comments - Due January 23, 2020 at 4:00 p.m.
- Econox Renewables Inc.'s Comments (1/23/20)
- Green Development LLC's Comments (1/23/20)
- National Grid's Comments (1/23/20)
- Heartwood Group, Inc.'s Comments (2/24/20)
- PUC Notice of Oral Arguments - February 25, 2020 @ 1:00 PM
- PUC Order No. 23811 issued the Episcopal Diocese Rhode Island on its Petition for Declaratory Judgment submitted on October 11, 2019. Order issued 4/14/20.
- Report and Order 23811 was appealed to the Supreme Court by EDRI